Search Results
-
KP-1507-R2 - Klamath Project; Using 2" X 4" strike-off, the improvement in the surface, caused by the second pass of the 4" X 6" strike-off, is readily noted above the 2" X 4" strike-off; July 18, 1947; ...
Citation -
KP-1508-R2 - Klamath Project; Using wood bull float after striking off with 2 x 4; Time approximately 1:40 P. M., July 18, 1947; Stacy, contractor; Photo by H. W. Sexton
Citation -
KP-1509-R2 - Klamath Project; Using Fresno float (steel) after bull float; Time approximately 1:44 P. M., July 18, 1947; Stacy, contractor; Photo by H. W. Sexton
Citation -
KP-2569-R2-Klamath Project - TULE LAKE DIVISION - Sump 2, Specifications DC-5248, Q-2 Lateral. Water truck sprinkling material placed by Hancock Elevating Scraper for lining of Q-2 Lateral, Station 22+00 ...
Citation -
KP-2570-R2-Klamath Project - TULE LAKE DIVISION - Sump 2, Specifications DC-5248, Q-2 Lateral. Hancock Elevating Scraper Model 7E2 and John Deere Tractor, Model 840 placing lining material on Q-2 Lateral ...
Citation -
KP-2571-R2-Klamath Project - TULE LAKE DIVISION - Sump 2, Specifications DC-5307, R-Canal. Hancock Elevating Scraper, 8 cu. yd. capacity with sideboards, placing canal lining at Station 29+50, R-Canal; ...
Citation -
KP-2572-R2-Klamath Project - TULE LAKE DIVISION - Sump 2, Specifications DC-5307, R-Canal. John Deere tractor, Model A, pulling a 10-ton pneumatic roller to compact canal lining, Station 29+50, R-Canal; ...
Citation -
48. [Image] Main Canal, Div. 3
June 16, 1906; Originally #10 of a series of eighty seven photos; Photo by D.W.M. (may be initials of the Klamath Project engineer D.W. Murphy)Citation -
49. [Image] Main Canal, Div. 3
June 16, 1906; Originally #11 of a series of eighty seven photos; Photo by D.W.M. (may be initials of the Klamath Project engineer D.W. Murphy)Citation -
50. [Image] Work on Big Fill, Div. 3, Main Canal
August 15, 1906; Originally #34 of a series of eighty seven photos; Photo by D.W.M. (may be initials of the Klamath Project engineer D.W. Murphy)Citation