You searched for: Start Over History Remove constraint History Author Wamstad, C. O. Remove constraint Author: Wamstad, C. O. Subject Irrigation canals and flumes -- Linings Remove constraint Subject: Irrigation canals and flumes -- Linings Subject Irrigation projects Remove constraint Subject: Irrigation projects

Search Results

  • 2989
    KP-2190-R2--Lower Cost Canal Lining. Klamath Project. M-2-a Lateral. Flat-iron roller which has five 18" X 16" airplane tires. Used in compacting earth lining; April 13, 1953; Bureau of Reclamation Photo ...
    Citation
  • 2992
    KP-2193-R2--Lower Cost Canal Lining, Klamath Project. M-2-a Lateral, Station 150+00. General view of grader and rollers constructing compacted banks; April 13, 1953; Bureau of Reclamation Photo by C. O. ...
    Citation
  • 2994
    KP-2195-R2--Lower Cost Canal Lining. Klamath Project. M-2-a Lateral. Compacted earth lining. D-8 cat with dozer pulling in last lift for compacted bank; April 13, 1953; Bureau of Reclamation Photo by C. ...
    Citation
  • 2996
    KP-2197-R2--Lower Cost Canal Lining, Klamath Project. M-2-a Lateral. Compacted earth lining. Looking downstream from Sta. 143+00. Bottom section after winter's weathering; March 29, 1953; Bureau of Reclamation ...
    Citation
  • 2998
    KP-2199-R2--Lower Cost Canal Lining. Klamath Project. M-2-a-1 Lateral. End of 30-inch over-excavated section for compacted earth lining showing also, undisturbed ditch; April 13, 1953; Bureau of Reclamation ...
    Citation
  • 3013
    KP-2192-R2--Lower Cost Canal Lining, Klamath Project. M-2-a Lateral, Station 150+00. General view of grader and rollers constructing compacted banks. Next-to-last lift; April 13, 1953; Bureau of Reclamation ...
    Citation
  • 3022
    KP-2200-R2--Lower Cost Canal Lining. Klamath Project. M-2-a Lateral. Compacted Earth lining. 13-wheels- 6 front, 7 back. Wobble wheel rollers; April 13, 1953; Bureau of Reclamation Photo by C. O. Wamst...
    Citation
  • 3031
    KP-2203-R2 - Lower Cost Canal Lining - A-3 Lateral. Klamath Project.Over-excavation for buried Weather-Foil Roofing furnished by Certainteed Products Company; April 14, 1953; Bureau of Reclamation Photo ...
    Citation
  • 2993
    KP-2194-R2--Lower Cost Canal Lining, Klamath Project. M-2-a Lateral. Compacted earth lining. Looking upstream from Sta. 137+50. 18-ft. Bottom; two 6-inch layers in place; March 29, 1953; Bureau of Reclamation ...
    Citation
  • 2995
    KP-2196-R2--Lower Cost Canal Lining. Klamath Project. M-2-a-1 Lateral. Bottom of ditch, after standing from fall until spring, opened up for compacted earth lining. Discing to mix top, dry material with ...
    Citation