P12-201-4479 NA Klamath Project, OR-CA. Contractor had to pre-excavate sites where PP 'E' bridge piling would be driven. During construction of PP 'E', a pit run material was used for backfill. Apparently ...
Citation -
P12-201-4488 NA Klamath Project, OR-CA. Picture taken of RHC 1/4" steel plate to be used as a bulkhead in CMP "84" hydrostatic test. This one to be inserted in round CMP to concrete transition west of ...
Citation -
P12-201-4492 NA Klamath Project, OR-CA. Template being used over screeding in placing bedding material for 84" RCP; December 2, 1977; USBR photo by D.J. Kline
Citation -
P12-201-4501 NA Klamath Project, OR-CA. Center Canal Flume -- Photo shows crack on floor joint of flume after cleanup. These were dried using propane heaters overnight prior to repairs. These joint openings ...
Citation -
P12-201-4502 NA Klamath Project, OR-CA. Center Canal Flume -- View of west dike on inlet to flume. This was built up for flume repairs. Note portable gas dewatering pump at base of dike used for flume ...
Citation -
P12-201-4503 NA Klamath Project, OR-CA. Center Canal Flume -- Curing tent used in repair of joint (photos 4501NA & 4502NA of flume repairs). Also shows location of this joint in relation to flume wooden ...
Citation -
P12-201-4504 NA Klamath Project, OR-CA. Center Canal Flume -- Repaired joint shown in previous photos. Used a 6" neoprene waterstop and a 3 part PRC sealer. Also drilled 3/4" anchors on 6" alternating ...
Citation -
P12-201-4506 NA Klamath Project, OR-CA. Center Canal Flume -- View of floor and south wall looking down at the joint between the new and old portions of the flume. This joint was repaired using a rubber ...
Citation -
P12-201-4507 NA Klamath Project, OR-CA. Center Canal Flume -- View showing removal of Center Canal Flume inlet dike after completion of flume repairs. Case 580-C Extend-A-Hoe used for dike removal; January ...
Citation -
P12-201-4510 NA Klamath Project, OR-CA. Pumping Plant FF -- Photo shows north wall of siphon inlet transition after compacted backfill operations were approximately 50% completed. Note plastic covering ...
Citation