    P-12-201-4295 NA Klamath Project, OR-CA. Excavation of Pumping Plant EE site, using dragline. A 3500 Manitowoc crane with 1-yard bucket, was in use. Material encountered was same as indicated in Drawing ...
    Citation
  • 4378
    P-12-201-4297 NA Klamath Project, OR-CA. Work begins on dike to pretect (sic) jobsite from flooding in event pumping plants should shut off, causing Kl. Straits Drain to rise. Overall view of excavation ...
    Citation
  • 4381
    P-12-201-4300 NA Klamath Project, OR-CA. Completed dike between P Plant EE excavation and Kl. Str. Drain. View, looking east. of existing Plant E and excavation for Pumping Plant EE; December 1976; ...
    Citation
  • 4382
    P-12-201-4301 NA Klamath Project, OR-CA. Stripped and cured wing wall flume support for Center Canal outlet transition; December 1976; USBR photo by D. J. Kline
    Citation
  • 4383
    P-12-201-4302 NA Klamath Project, OR-CA. Crane moving to second landing to complete second half of Plant EE excavation. View Looking east; December 1976; USBR photo by D. J. Kline
    Citation
  • 4384
    P-12-201-4303 NA Klamath Project, OR-CA. Soldier piling (1'x1') driven to contractor's plan to a depth of ±9', to be used in conjunction with wood lagging to protect worker and work inside Plant EE work ...
    Citation
  • 4385
    P12-201-4304 NA Klamath Project, OR-CA. Snall (sic) leak developing on west bank about midway and ±6' down from excavation surface at Plant E; December 1976; USBR photo by D. J. Kline
    Citation
  • 4386
    P12-201-4305 NA Klamath Project, OR-CA. Dike built up another ±5' on inlet to Center Canal Flume; December 1976; USBR photo by D. J. Kline
    Citation
  • 4387
    P12-201-4306 NA Klamath Project, OR-CA. Nearly completed Plant EE excavation to depth elev. ±50. Water in excavation is due to the power being off to east side wells, for approximately 30 hours; December ...
    Citation
  • 4388
    P12-201-4307 NA Klamath Project, OR-CA. Trimming of side walls at Plant EE to better expedite a ± 1 to 1½/1 slope; December 1976; USBR photo by D. J. Kline
    Citation