Search Results
-
151. [Image] KSD Enlargement, Lower Klamath Lake Division, Specs. 200C-922 - Patterson Constr. Co., Contractor
P-12-200-4218NA Klamath Project - Oregon-California. Northwest 80-D dragline excavating drain section at Sta. 302±. This is the oxbow area where new channel is to be constructed. Note that very little ...Citation -
152. [Image] KSD Enlargement, Lower Klamath Lake Division, Specs. 200C-922 - Patterson Constr. Co., Contractor
P-12-200-4219NA Klamath Project - Oregon-California. Northwest 80-D dragline excavating drain section at Sta. 302±. This is the oxbow area where new channel is to be constructed. Note that very little ...Citation -
153. [Image] KSD Enlargement, Lower Klamath Lake Division, Specs. 200C-922 - Patterson Constr. Co., Contractor
P-12-200-4220-Klamath Project - Oregon-California. Borrow pit for sub-base material for road to be constructed on west bank of drain. Material was very tight and had to be ripped by a D-8 dozer. Four ...Citation -
154. [Image] Another view of borrow pit for sub-base material for road to be constructed on west bank of drain
P-12-200-4221NA Klamath Project - Oregon-California. Four c.y. caterpillar loader is loading 20 c.y. belly dump; August 1976; USBR photo by D. W. SteinCitation -
155. [Image] KSD Enlargement, Lower Klamath Lake Division, Specs. 200C-922 - Patterson Constr. Co., Contractor
P-12-200-4222NA Klamath Project - Oregon-California. Borrow pit for sub-base material for road to be constructed on west bank of drain. Material was very tight and had to be ripped by a D-8 dozer. ...Citation -
156. [Image] KSD Enlargement, Lower Klamath Lake Division, Specs. 200C-922 - Patterson Constr. Co., Contractor
P-12-200-4223NA Klamath Project - Oregon-California. Borrow pit for finish grade material for road to be constricted on west bank of drain. D-8 dozer ripping material and 4 c.y. caterpillar loading 20 ...Citation -
157. [Image] KSD Enlargement, Lower Klamath Lake Division, Specs. 200C-922 - Patterson Constr. Co., Contractor
P-12-200-4224NA Klamath Project - Oregon-California. Another view of borrow pit for finish grade material for road to be constructed on west bank of drain. D-8 dozer ripping material and 4 c.y. caterpillar ...Citation -
158. [Image] KSD Enlargement, Lower Klamath Lake Division, Specs. 200C-922 - Patterson Constr. Co., Contractor
P-12-200-4225NA Klamath Project - Oregon-California. View looking west of two Motor Graders in final stages of grading west bank of drain; August 1976; USBR photo by D. W. SteinCitation -
159. [Image] KSD Enlargement, Lower Klamath Lake Division, Specs. 200C-922 - Patterson Constr. Co., Contractor
P-12-200-4226NA Klamath Project - Oregon-California. Model No. 12 Motor Grader leveling and shaping finish grade material on road to be constructed on west bank of drain. View looking north; August ...Citation -
160. [Image] KSD Enlargement, Lower Klamath Lake Division, Specs. 200C-922 - Patterson Constr. Co., Contractor
P-12-200-4227NA Klamath Project - Oregon-California. A 966-C Loader pulling a Hyster grid roller on sub-base material on road to be constructed on west bank of the drain. Contractor elected to consolidate ...Citation