P12-201-4284 NA Klamath Project OR-CA. Entire length of water jet pipe (40' long) and 3" in diameter; January 4, 1977; USBR photo by D. J. Kline
Citation -
P12-201-4285 NA Klamath Project OR-CA. Water jet pump and power supply mounted on flat bed. Used for water jetting 2 piles, Center Canal flume pier; January 4, 1977; USBR photo by D. J. Kline
Citation -
P12-201-4286 NA Klamath Project OR-CA. Overall view of leads with Vulcan 1 hammer and water jet pipe and 4" hose leading to it. In background is a dewatering pump. Center Canal flume; January 7, 1977; ...
Citation -
P12-201-4287 NA Klamath Project OR-CA. Closer view of water jetting preparation. Note two pile bucks setting water jet; January 7, 1977; USBR photo by D.J. Kline
Citation -
P12-201-4288 NA Klamath Project OR-CA. Results of 1/7 water jetting. Note two piling (upper right and center right). These were the two piling jetted to 35' depth; January 10, 1977; USBR photo by D. ...
Citation -
P12-201-4289 NA Klamath Project OR-CA. Tying rebar in place for flume pier base (footing); January 13, 1977; USBR photo by D. J. Kline
Citation -
P12-201-4290 NA Klamath Project OR-CA. 3/4-yard bucket used with Manitowoc 3500 dragline to lift concrete from transit mixer to pier (excavation site). Center Canal flume in background; January 14, 1977; ...
Citation -
P12-201-4291 NA Klamath Project OR-CA. Finishing of pier slab; pier extension rebar also shown. Center Canal Flume; January 14, 1977; USBR photo by D. J. Kline
Citation -
P12-201-4292 NA Klamath Project OR-CA. Curing protection for below freezing conditions. Bisqueen tent and in background, note 10 gal. propane tank with radiant heater placed inside tent. Pier footing ...
Citation -
P12-201-4294 NA Klamath Project OR-CA. Pumping Plant EE piling for Bent No. 1 background, and Bent No. 2 in place. Required extra piling foreground, left, as piling next to it didn't meet specs. design. ...