P12-201-4380 NA Klamath Project, OR-CA. Pumping Plant FF--View looking southeast: slab completed. Burke-White pigmented curing compound has been applied by spray. Three smudge pot heaters placed in ...
Citation -
P12-201-4381 NA Klamath Project, OR-CA. Pumping Plant EE--Preparation for placement of pump deck (Elev. B) slab. Note contractor wetting down rebar prior to placement; May 20, 1977; USBR photo by D. ...
Citation -
P12-201-4382 NA Klamath Project, OR-CA. Pumping Plant EE--Note carpenters re-checking elevations on miscellaneous metals and concrete screeds; May 20, 1977; USBR photo by D. J. Kline
Citation -
P12-201-4383 NA Klamath Project, OR-CA. Pumping Plant EE--Placement of final section of Plant EE Elev. B slab; May 20, 1977; USBR photo by D. J. Kline
Citation -
P12-201-4384 NA Klamath Project, OR-CA. Center Canal Flume--North side of flume joint--Separation of old flume and newly constructed section of flume;separation at top was .21 of a foot at the worst point. ...
Citation -
P12-201-4385 NA Klamath Project, OR-CA. Center Canal Flume--RHC Construction applied 3 of these metal retaining clamps and also 4x14" kick braces to both sides of flume wall; May 24, 1977; USBR photo ...
Citation -
P12-201-4386 NA Klamath Project, OR-CA. Laborers working on compacted backfill on east side of Pumping Plant EE. Wackers were used on 6" lifts along sides close to structure. Five ton vibratory roller ...
Citation -
P12-201-4387 NA Klamath Project, OR-CA. Backfill on back of Oregon outlet side of Plant EE. Took contractor about 11 days to complete backfill on Plant EE; June 3, 1977; USBR photo by D. J. Kline
Citation -
P12-201-4388 NA Klamath Project, OR-CA. Inlet to Plant EE after nearly 2 inches of rain in a 5-hour period. Power to dewater pumps was lost due to lightning knocking out transformer. Power was out for ...
Citation -
P12-201-4390 NA Klamath Project, OR-CA. View of four piling being driven on south side of flume prior to cutoff; June 16, 1977; USBR photo by D. J. Kline
Citation