You searched for: Start Over Irrigation Remove constraint Irrigation Author United States. Bureau of Reclamation Remove constraint Author: United States. Bureau of Reclamation Subject Klamath Project (U.S.) -- History Remove constraint Subject: Klamath Project (U.S.) -- History Subject Pumping stations -- Design and construction Remove constraint Subject: Pumping stations -- Design and construction Material Types Image Remove constraint Material Types: Image Database Klamath Waters Library Remove constraint Database: Klamath Waters Library

Search Results

  • 4480
    P12-201-4398 NA Klamath Project, OR-CA. Pumping Plant FF inlet transition floor placement. E-Con placer used to transfer concrete form transit mixer to pour site; July 28, 1977; USBR photo by D.J. Kli...
    Citation
  • 4481
    P12-201-4399 NA Klamath Project, OR-CA. Pumping Plant FF-Concrete placed in wall in 2 ft. lifts and vibrated by means of two small hand-held electric vibrators; August 5, 1977; USBR photo by D.J. Klin...
    Citation
  • 4486
    P12-201-4404 NA Klamath Project, OR-CA. Pumping Plant EE--Completed inlet transition on west side. Walls were form cured in 14 days; August 3, 1977; USBR photo by D.J. Kline
    Citation
  • 4487
    P12-201-4405 NA Klamath Project, OR-CA. Pumping Plant EE completed inlet transition on east side; August 3, 1977; USBR photo by D.J. Kline
    Citation
  • 4488
    P12-201-4406 NA Klamath Project, OR-CA. Pumping Plant EE--East side retaining wall with slab and footing ready for placement; July 27, 1977; USBR photo by D.J. Kline
    Citation
  • 4489
    P12-201-4407 NA Klamath Project, OR-CA. Overall view of front portion of Plant EE second lift. Walls and retaining walls have concrete forms in place; August 3, 1977; USBR photo by D.J. Kline
    Citation
  • 4491
    P12-201-4409 NA Klamath Project, OR-CA. Pumping Plant EE--Outlet structure slab poured and Burke curing compound sprayed on. Slab extended 2 ft. further east and west as per Inspector's instructions. ...
    Citation
  • 4502
    P12-201-4420 NA Klamath Project, OR-CA. View of cold joint between Plant EE east retaining wall and wing wall indicates apparent settling of retaining wall which is presently stabilized; August 24, 1977; ...
    Citation
  • 4505
    P12-201-4424 NA Klamath Project, OR-CA. Pumping Plant FF--stripped second lift walls. Note small white line midway up wall indicating cold joint due to pumper (concrete) breakdown; August 29, 1977; ...
    Citation
  • 4508
    P12-201-4427 NA Klamath Project, OR-CA. Pumping Plant FF--Inoperable screw gates where Ady Canal runs under Klamath Straits Drain. Screw gates on siphon; August 29, 1977; USBR photo by D.J. Kline
    Citation