  • 4470
    P12-201-4388 NA Klamath Project, OR-CA. Inlet to Plant EE after nearly 2 inches of rain in a 5-hour period. Power to dewater pumps was lost due to lightning knocking out transformer. Power was out for ...
    Citation
  • 4472
    P12-201-4390 NA Klamath Project, OR-CA. View of four piling being driven on south side of flume prior to cutoff; June 16, 1977; USBR photo by D. J. Kline
    Citation
  • 4473
    P12-201-4391 NA Klamath Project, OR-CA. View of piling on north side of flume. Also note temporary pier built on piling originally used by contractor for false work in construction of flume; June 16, 1977; ...
    Citation
  • 4474
    P12-201-4392 NA Klamath Project, OR-CA. Center Canal Flume--View of flume repairs. 24" CMP for supplying irrig. water to ranchers while allowing work inside flume. Nine 1-inch temporary flume tie rods ...
    Citation
  • 4475
    P12-201-4393 NA Klamath Project, OR-CA. Center Canal Flume--View of north wall showing a large pocket discovered in pier fillet area. This was patched with an epoxy sand mixture; July 9, 1977; USBR photo ...
    Citation
  • 4477
    P12-201-4395 NA Klamath Project, OR-CA. Pumping Plant EE--Installation of 48" RCP outlet pipes. Checking placements prior to adding second section of pipe. Note cradle excavated for 48" RCP and extra ...
    Citation
  • 4478
    P12-201-4396 NA Klamath Project, OR-CA. Pumping Plant FF--View of inlet transition with cutoff wall formed and backfill completed just prior to installation of steel; July 18, 1977; USBR photo by D.J. ...
    Citation
  • 4479
    P12-201-4397 NA Klamath Project, OR-CA. Pumping Plant FF inlet transition resteel and forms for bottom slab placement; July 26, 1977; USBR photo by D.J. Kline
    Citation
  • 4480
    P12-201-4398 NA Klamath Project, OR-CA. Pumping Plant FF inlet transition floor placement. E-Con placer used to transfer concrete form transit mixer to pour site; July 28, 1977; USBR photo by D.J. Kli...
    Citation
  • 4481
    P12-201-4399 NA Klamath Project, OR-CA. Pumping Plant FF-Concrete placed in wall in 2 ft. lifts and vibrated by means of two small hand-held electric vibrators; August 5, 1977; USBR photo by D.J. Klin...
    Citation