    P12-201-4381 NA Klamath Project, OR-CA. Pumping Plant EE--Preparation for placement of pump deck (Elev. B) slab. Note contractor wetting down rebar prior to placement; May 20, 1977; USBR photo by D. ...
    Citation
  • 4464
    P12-201-4382 NA Klamath Project, OR-CA. Pumping Plant EE--Note carpenters re-checking elevations on miscellaneous metals and concrete screeds; May 20, 1977; USBR photo by D. J. Kline
    Citation
  • 4465
    P12-201-4383 NA Klamath Project, OR-CA. Pumping Plant EE--Placement of final section of Plant EE Elev. B slab; May 20, 1977; USBR photo by D. J. Kline
    Citation
  • 4468
    P12-201-4386 NA Klamath Project, OR-CA. Laborers working on compacted backfill on east side of Pumping Plant EE. Wackers were used on 6" lifts along sides close to structure. Five ton vibratory roller ...
    Citation
  • 4469
    P12-201-4387 NA Klamath Project, OR-CA. Backfill on back of Oregon outlet side of Plant EE. Took contractor about 11 days to complete backfill on Plant EE; June 3, 1977; USBR photo by D. J. Kline
    Citation
  • 4470
    P12-201-4388 NA Klamath Project, OR-CA. Inlet to Plant EE after nearly 2 inches of rain in a 5-hour period. Power to dewater pumps was lost due to lightning knocking out transformer. Power was out for ...
    Citation
  • 4476
    P12-201-4394 NA Klamath Project, OR-CA. Pumping Plant EE--View of inlet transition steel, showing finished product of original steel and added steel. Photo taken on east side of inlet just before tying ...
    Citation
  • 4477
    P12-201-4395 NA Klamath Project, OR-CA. Pumping Plant EE--Installation of 48" RCP outlet pipes. Checking placements prior to adding second section of pipe. Note cradle excavated for 48" RCP and extra ...
    Citation
  • 4478
    P12-201-4396 NA Klamath Project, OR-CA. Pumping Plant FF--View of inlet transition with cutoff wall formed and backfill completed just prior to installation of steel; July 18, 1977; USBR photo by D.J. ...
    Citation
  • 4479
    P12-201-4397 NA Klamath Project, OR-CA. Pumping Plant FF inlet transition resteel and forms for bottom slab placement; July 26, 1977; USBR photo by D.J. Kline
    Citation