Search Results
-
P12-201-4361 NA Klamath Project, OR-CA. Pumping Plant FF slab concrete placement. View shows placing concrete for first lift. (Slab was placed in two lifts). Vibration was by means of two air-powered vibrators ...
Citation -
P12-201-4362 NA Klamath Project, OR-CA. Plant FF - Driving 1:2 batter piles at plant FF site. Manitowoc 2900 crane with 90 ft. leads using 50-C hammer, driven by Clayton Steam Generator. View looking ...
Citation -
P12-201-4363 NA Klamath Project, OR-CA. Plant FF--Manitowoc 1900 Crane with 95 ft. boom and 90 ft. of leads driving batter pile at Plant FF site. Clayton Steam Generator mounted on rear of crane used ...
Citation -
P12-201-4364 NA Klamath Project, OR-CA. Pumping Plant EE--E-Con placer with 50 ft. of 5" lining, placing concrete for walls at Plant EE. Placed an average of 40 cu. yds. per hour. Concrete was batched ...
Citation -
P12-201-4365 NA Klamath Project, OR-CA. Willamette Western getting 2900 Manitowoc into Plant FF excavation to drive timber piling; April 14, 1977; USBR photo by D. J. Kline
Citation -
P12-201-4366 NA Klamath Project, OR-CA. Setting rebar in place for wall placement at Plant EE. Notice 1 wall of forms in place, and preparation underway for setting other wall where resteel in place; ...
Citation -
P12-201-4375 NA Klamath Project, OR-CA. Pumping Plant EE--Photo showing repair to torn gusset plate on boom of RHC's Manitowoc 3500 crane. It was repaired with ¼" steel plate by a certified welder; May ...
Citation -
P12-201-4376 NA Klamath Project, OR-CA. Pumping Plant FF--Photo inside middle bay looking at placement below Elev. B for the 2 ft. thick wall. Note E-Con placer "elephant trunk" dispersing concrete; May ...
Citation -
P12-201-4377 NA Klamath Project, OR-CA. Pumping Plant FF--View looking south of concrete placement for walls up to base of Elev. B slab; May 31, 1977; USBR photo by D. J. Kline
Citation -
P12-201-4378 NA Klamath Project, OR-CA. Pumping Plant FF--View looking west at placement for slab foundation. E-Con placer setting up to unload mixer truck; May 1977; USBR photo by D. J. Kline