You searched for: Start Over Photos Remove constraint Photos Author Bergloff, Andrew M. Remove constraint Author: Bergloff, Andrew M.

Search Results

  • 2372
    KP-1869 - Klamath Project. Lower Cost Canal Lining - N-16 Lateral. Detail of buried asphalt membrane on north side. Picture shows condition of seam at bottom of slope. A small wrinkle has flattened ...
    Citation
  • 2373
    KP-1870 - Klamath Project. Lower Cost Canal Lining - N-16 Lateral. Same as No. 1869 [handwritten, number "22" crossed out] with seam cut open. Due to the short length of time membrane is not completely ...
    Citation
  • 2374
    KP-1871 - Klamath Project. Lower Cost Canal Lining - N-16 Lateral. Same Sta ["Sta" is inserted handwritten] as No. 1869 + 70 [handwritten, number "22" crossed out] showing same condition on south side ...
    Citation
  • 2375
    KP-1872 - Klamath Project. Lower Cost Canal Lining - N-16 Lateral. Sta. 83-00, north side of channel. Picture reveals wrinkle where asphalt did not seal. Also a crack is uncovered which had been doctored ...
    Citation
  • 2387
    KP-1884 - Klamath Project. N-16 Lateral. Lower cost canal lining. Laying of second strip of asphalt membrane with approximately 2-inch overlap. George L. Browning and L. G. Oliensis on far side of ...
    Citation
  • 2394
    KP-1891 - Klamath Project. Lower cost canal lining. This shows the dipping process which took the place of painting each side of the asphalt strips with a brush. A. J. Lommasson, instructing. Plant ...
    Citation
  • 2395
    KP-1892 - Klamath Project. Lower cost canal lining. Heating shack in background. Due to cold weather, asphalt sheets cracked when unrolled, so rolls were put inside building to be kept warm; December ...
    Citation
  • 2398
    KP-1895 - Klamath Project. Lower Cost Canal Lining. Picture shows asphalt sheets as will be left for backfill. Overlapping edges are not welded whatsoever. Edges are poured with asphalt compound, RC-0 ...
    Citation
  • 2401
    KP-1989 - Klamath Project. Lower cost canal lining. Close-up of process of flowing RC-0 compound on asphalt. A 3' x 2" pipe with one end smashed into a spatula shape is welded on to a flower watering ...
    Citation
  • 2406
    KP-1904 - Klamath Project. Lower Cost Canal Lining. N-16 Lateral. Between Sta. 84-30 & 84-60, a transition takes place where the regular 10-ft. bottom becomes a 6-ft. bottom. Picture shows also the ...
    Citation